Hoffman Lofts
Status
Pending
Company & Contacts
SLDC
Advantes Group, Jacob Surratt
Location
700-702 N. 2nd St., St. Louis, MO 63102
Mandatory use of GPTS and Headcount.
Ordinance No. 69427
For each Public Works Contract, Abated Project, TIF Project, and City of St. Louis 5 Bonded Project for which the design team’s estimated base value of the contract is one-million 6 dollars ($1,000,000) or more, each Labor Hour shall be paid at a rate that is no less than that of 7 the area’s standard prevailing wages as provided and determined under the mechanism 8 described in RsMO 290.210 – 290.340 as such statutes now exist as of November 1, 2019
Ordinance No. 70767
City of St. Lois MWBE Program Requires
African American 21%
Hispanic 2%
Asian American .5%
Native American .5%